(Created page with "Work In Progress.. == Implementation details == == Possible future extension == == Schedule == == Who will use results of this project == == Student's Biography ==...") |
|||
Line 11: | Line 11: | ||
+ | {| class="wikitable" | ||
+ | |- | ||
+ | ! Timeline !! TODO !! Status | ||
+ | |- | ||
+ | | 23 - 31 May 2016 || | ||
+ | * Voxel model implementation in Nasa WebWorldWind. | ||
+ | || Done | ||
+ | |- | ||
+ | | 1 – 10 June 2016 || | ||
+ | * Sample grid and data importing | ||
+ | || Done | ||
+ | |- | ||
+ | | 11 - 17 June 2016 || | ||
+ | * Sample visualization on voxel | ||
+ | * Multi dimensions on a single voxel | ||
+ | || --- | ||
+ | |- | ||
+ | | 18 – 25 June 2016 || | ||
+ | * Matching voxels with real data. | ||
+ | * Creating the first filtering functionalities | ||
+ | || --- | ||
+ | |- | ||
+ | | 26 June - 2 July 2016 || | ||
+ | * Advanced filtering functionalities | ||
+ | || --- | ||
+ | |- | ||
+ | | 3 - 17 July 2016 || | ||
+ | * Time slider (4th dimension) implementation. | ||
+ | || --- | ||
+ | |- | ||
+ | | 18 – 31 July 2016 || | ||
+ | * Sample database implementation | ||
+ | || --- | ||
+ | |- | ||
+ | | 1 – 15 August 2016 || | ||
+ | * Importing of diverse datasets. | ||
+ | || --- | ||
+ | |- | ||
+ | | 16 – 23 August 2016 || | ||
+ | * User interface implementation | ||
+ | * Testing and documentation | ||
+ | || --- | ||
+ | |} | ||
+ | |||
+ | We will try to follow the schedule and report the status of the project each week. | ||
== Who will use results of this project == | == Who will use results of this project == |
Revision as of 02:05, 28 May 2016
Work In Progress..
Implementation details
Possible future extension
Schedule
Timeline | TODO | Status |
---|---|---|
23 - 31 May 2016 |
|
Done |
1 – 10 June 2016 |
|
Done |
11 - 17 June 2016 |
|
--- |
18 – 25 June 2016 |
|
--- |
26 June - 2 July 2016 |
|
--- |
3 - 17 July 2016 |
|
--- |
18 – 31 July 2016 |
|
--- |
1 – 15 August 2016 |
|
--- |
16 – 23 August 2016 |
|
--- |
We will try to follow the schedule and report the status of the project each week.