Line 127: Line 127:
 
* [https://github.com/Maureque/gvsig-gsoc2019-topology/blob/master/reports/Bonding%20Period%20report.pdf COMMUNITY BONDING PERIOD (May 6th – May 27th).]
 
* [https://github.com/Maureque/gvsig-gsoc2019-topology/blob/master/reports/Bonding%20Period%20report.pdf COMMUNITY BONDING PERIOD (May 6th – May 27th).]
 
* [https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Report-Week-1-(May-27th-to-June-2nd) Report Week 1 (May 27th to June 2nd).]
 
* [https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Report-Week-1-(May-27th-to-June-2nd) Report Week 1 (May 27th to June 2nd).]
 +
* [https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Report-Week-2-(June-3rd-to-June-9th) Report Week 2 (Week 2 (June 3rd - June 9th).]
  
 
== References==
 
== References==

Revision as of 22:00, 6 June 2019

Project

Title: New rules for the Topology Framework in gvSIG Desktop.

Student: Mauro Carlevaro.

Mentors: Óscar Martínez, Mario Carrera Rodriguez, Alfred de Jager and Francisco Peñarrubia.

Repository: Link to GitHub repository.

Brief Description

A new topology toolbox. This tool will provide a group of integrity rules that will check the validation of the geometries relationship in the data. A new topology data model can be created for each project. This toolbox provide a new set of tools to navigate, find and fix validation errors different from each topology rule. Right now, there are just a few topology rules implemented with a limited actions. This project will analize, implement and optimize a new set of rules that will be incorporated to this framework. This tools can be created in Java or in Jython through the Scripting composer tool.

State of the Project Before GSoC.

Only a few topology rules have been implemented until now, the most of them are still pending to be developed.

The addition that the project bring to the software.

A new set of topology rules for vector datasets validation and fixing is implemented, which improve and expand the existing before.

Deliverables

A new set of topology rules for vector datasets validation/fixing, that will improve and expand the existing one:

  • Must be coincident with..
  • Must be covered by endpoint of.
  • Points must be covered by line.
  • Must be properly inside polygons (PointMustBeProperlyInsidePolygonRule)
  • Must be covered by boundary of.
  • Must not overlap (Must not overlap polygon).
  • Must not have gaps.
  • Contains point.
  • Contains one point.
  • Must not overlap with.
  • Must be covered by.

Timeline

Pre Coding Period

Pre-Bonding Period (March 25th - April 9th)

  • Set up working environment, choose tools to be used in the project and set up repository.
  • Familiarize more deeply with the community.
  • Review and learn as much as possible about Python, Jython and Java.
  • Test the topology plugin and study the code of some rules that are already made.

Community Bonding Period (May 6th - May 27th)

  • Familiarize more deeply with the code, with the mentors of the project and with the documentation.
  • Study the Topology Framework API.
  • Study the algorithm for a correct implementation according to the established rules.
  • Set up the development environment.
  • Interact with mentors, introduce myself to the community and actively get involved in the discussion.
  • Set up the wiki page to keep track of weekly progress.
  • Introduce myself and the project on OSGeo's SOC mailing list.
  • Improve in the creation of scripts

Coding Period

First Evaluation Period (May 27th - June 23rd)

  • Week 1 (May 27th - June 2nd)
 √ Define all the required, all the corresponding Classes and Objects.
 √ Define the interactions.
 √ Topological rule: Must be coincident with. Link: https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Must-be-coincident-with.
 √ Weekly report. Link: https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Report-Week-1-(May-27th-to-June-2nd).
  • Week 2 (June 3rd - June 9th)
 - Topological rule: Must be coincident with. Topological rule integration with the topology framework.    
   Link: https://github.com/Maureque/TopologyRuleMustBeCoincidentWithPoint
 - Test and debug the developed code. 
 √ Weekly report. Link: https://github.com/Maureque/gvsig-gsoc2019-topology/wiki/Report-Week-2-(June-3rd-to-June-9th)
  • Week 3 (June 10th - June 16th)
 - Topological rule: Must be covered by endpoint of.
 - Test and debug the developed code. 
 - Test and document existing code more thoroughly.
 - Weekly report.
  • Week 4 (June 17th - June 23rd)
 - Topological rule: Must be covered by endpoint of.
 - Topological rule: Points must be covered by line.
 - Test and document existing code more thoroughly.
 - Weekly report.

June 24th (beginning)- June 28th (deadline).

  • Submit Evaluations.

Second Evaluation Period (June 24th - July 21st)

  • Week 5 (June 24th - June 30th)
 - Topological rule: Must be properly inside polygons (PointMustBeProperlyInsidePolygonRule).
 - Weekly report.
  • Week 6 (July 1st - July 7th)
 - Topological rule: Must be covered by boundary of.
 - Optimize algorithms.
 - Weekly report.
  • Week 7 (July 8th - July 14th)
 - Topological rule: - Must not overlap (Must not overlap polygon).
 - Optimize algorithms.
 - Test and debug the developed code.
 - Test and document existing code more thoroughly.
 - Weekly report.
  • Week 8 (July 15th - July 21st)
 - Topological rule: - Must not have gaps.
 - Test and debug the developed code.
 - Test and document existing code more thoroughly.
 - Weekly report.

July 22nd (beginning)- July 26th (deadline).

  • Submit Evaluations.

Third Evaluation Period (July 22nd - August 18th)

  • Week 9 (July 22nd - July 28th)
 - Topological rule: Contains point.
 - Topological rule: Contains one point.
 - Test, debug and improve the developed code.
 - Weekly report.
  • Week 10 (July 29th - August 4th)
 - Topological rule: Must not overlap with.
 - Test, debug and improve the developed code.
 - Generate documentation specially oriented to users without any programming knowledge. 
 - Weekly report.
  • Week 11 (August 5th - August 11th)
 - Topological rule: Must be covered by.
 - Make further changes in the code to improve the functionality.
 - Improve existing documentation.
 - Weekly report.
  • Week 12 (August 12th - August 18th)
 - Make further changes in the code to improve the functionality.
 - Improve existing documentation.
 - Weekly report.
  • August 19th (beginning)- August 26th (deadline).
 - Submit Final work product and evaluations.

Weekly Reports

Section for listing the links to the weekly reports.

References

Student Information

Country: Uruguay

School and Degree:

  • Technological University (UTEC, Fray Bentos, Uruguay), Student of Bachelor of IT (2019-2022).
  • University of Engineering (ORT, Montevideo, Uruguay), Programmer Analyst (2014-2018).
  • University of Engineering (UdelaR, Montevideo, Uruguay), Cartographic Technician (2013-2016).

Computing experience

I have been working as a web developer and implementing geographic information systems. The technologies that i work with daily are: Java, Python, MySQL, PostgreSQL/PostGIS, Apache Tomcat and GeoServer.

GIS experience as a user

I have experience using gvSIG and QGIS. Thematic cartography course (Uruguay edition), dictated by The National Geographic Institute and the National Geographic Information Center of Spain. 40 hours duration. Participation in the webinar “gvSIG applied to wildlife and protected natural spaces", on October 14, 2014, made by MundoGEO and Asociación gvSIG, with 60 minutes duration.

GIS programming